2021

The Lake Crossing Swim were won by Anna Obieglo, in a new record time of 27:47 minutes, and Nate Holmes, with 150 swimmers participating. Due to the Corona hygiene regulations, participants were divided into start groups of 20 swimmers each. Starts were also conducted with a time gap between them.

16.09. Annual general meeting takes place
Vote on the planning of a new building at the Wörthsee.
The members' meeting votes on the proposal to commission a draft plan for a new club house with a cost framework of approximately 25,000 EUR.
The proposal is approved with 42 votes (no opposing votes, no abstentions)

Autumn
Formation of a building team:
Bettina Albrecht, Tobias Bartschinski, Manuel di Nardo, Tobias Dopfer, Klaus Engelbrecht, Alexander Held, Heike Janetzko, Chrissi Kronseder, Andi Sirch, Tobias Strassl, Marion Traub, Holger Zerbs
Offer from multiple architects: The building team decided on Ulrich Peter Hackl, Dipl.-Ing.-FH Architect, master of engineering
Development of the house design
Cost calculation prepared by architect U. Hackl

2022

28.03. Annual general meeting
„The members' meeting authorizes and empowers the entire board to arrange the demolition and construction of the club house, and to conclude the necessary contracts with the respective contractors. The costs for this amount to approximately 900,000 EUR. This is an estimate based on the available offers and calculations. The board requests approval, plus approximately 20% buffer for unforeseen expenses, totaling 1,100,000 EUR.
The costs for the measure (demolition and construction of the club house) will be financed with approximately 400,000 EUR of own capital and up to 700,000 EUR of foreign capital through a bank loan. In this context, the members' meeting authorizes the board to conclude a loan agreement of up to 700,000 EUR with a lender.“
The decision is adopted by the members' meeting with 43 votes and 2 abstentions.

30.07. - The Lake Crossing Swim won Anna Obieglo with Anna-Lena Maiberger and Nate Holmes with Jakob Obieglo. The women, as well as the men, touched the wall at the same time, thus there were four winners this year. 189 swimmers participated, new participant record. The summer festival was also well attended.

New Building

Loan
Offers from several banks were collected, finally the construction team decided on VR Bank
Signature of the board for the construction loan with VR Bank: 20 July

Funding:
Landeshauptstadt München rejects the request, as the club's land does not lie within the city of Munich
BLSV: provides a grant of up to a maximum of 50.000 EUR
KFW: the effort and costs exceed the funding conditions

Donations:
10.000 EUR until 17 July via homepage call, 1. donation target reached
20.000 EUR until 10.09.2022 / 2. donation target reached
30.000 EUR until 04.02.2023 / 3. donation target reached

Donation dinner on 17 July

Further:

Drainage plans are being drawn up
House design is being refined
Kitchen is being finalized
Construction insurance (building and liability) is being renewed.

Several offers were received, and the construction team chose the following companies:
Construction power: Electrician Maletz
Earthwork: Keller Earth Movements
Basement construction: Hans Greimel Beteiligungs GmbH Construction Company
Timber house: Aicher Timber House GmbH
Lifting equipment: Klaus Engelbrecht

Submission of the building application:
Municipality approved the application in May
District office approved the application: still pending
Signature of the construction contract: 12.09.
Signature of notary / mortgage: 16.09.

Bauteam meeting starting from August, every two weeks on Sundays at 6 PM, either online or at the lake

New construction:

Start of demolition under the leadership of Tobias Dopfer
Thank you also on this occasion to the many helpers who worked diligently during the demolition.

09.09. The house is being cleared and transported to the winter storage, the kitchen is being expanded and partially set up in the „washing room“.
10.09. Demolition party
Demolition 9.9. - 15.10.

{loadposition slider_neubau}

Further planned dates for the new building - Completion planned by the end of November 2023!

Basement excavation
From calendar week 15 to 17

Basement construction 
Planned start calendar week 18
Completion of basement expected by the end of calendar week 21

House construction
Company Aicher Projekt GmbH and Co KG
Planning since September 2022

House production
Planned start of timber house from calendar week 22

Interior finishing
Planned for late summer/autumn 2023

Outdoor facilities
In planning